Due date: Friday April 20thThe City of Spunkindale is planning a new water treatment plant. There are two possible water sources, Spunkin aquifer and flatbed aquifer. The only known problem with either water source is hardness. Estimate the chemicals required and the sludge production per million gallons of water for softening both of the source waters. Which water will create the greatest sludge mass? Which water will require the greatest amount of chemicals? Recent water reports are shown below. A spreadsheet is provided for you to complete your calculations. Use only this spreadsheet. Spunkin Aquifer:
Flatbed Aquifer:
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||